Problem 1
The following data were obtained from a project to create a new portable electronic.
Activity
Duration
Predecessors
5 Days
6 Days
8 Days
4 Days
3 Days
5 Days
5 Days
9 Days
12 Days
Step 1: Construct a network diagram for the project.
Step 2: Answer the following questions: (15 points total)
What is the Scheduled Completion of the Project? (5 points)
32
What is the Critical Path of the Project? (5 points)
B-D-F-G-I
What is the ES for Activity D? (1 points)
6
What is the LS for Activity G? (1 points)
15
What is the EF for Activity B? (1 points)
6
What is the LF for Activity H? (1 points)
32
What is the float for Activity I? (1 points)
0
Problem 2
The following data were obtained from a project to build a pressure vessel:
Activity
Duration
Predecessors
6 weeks
6 weeks
5 weeks
4 weeks
5 weeks
7 weeks
D, E, G
4 weeks
8 weeks
5 weeks
3 week
Step 1: Construct a network diagram for the project.
Step 2: Answer the following questions: (15 points total)
Calculate the scheduled completion time. (5 points)
30
Identify the critical path (6 points)
B-C-D-F-H
What is the slack time (float) for activity A? (1 points)
5
What is the slack time (float) for activity D? (1 points)
0
What is the slack time (float) for activity E? (1 points)
4
What is the