Lubricating Oil CompanyEssay title: Lubricating Oil CompanyProjectComputer SimulationLubricating OIL COMPANY1. Problem FormulationA manufacturing system produces Lubricating oil: P1, P2, and P3. There are four Vacuum Distillation Unit (labeled DU1 – DU4), three Extraction Unit (EU1 – EU3), two Removal Unit (RU1 – RU2), two Additive Unit (AU1 – AU2).

All products require a deterministic transit time to move from one process to the next. When the parts arrive at a Unit station, they are placed in a buffer for holding. I assume that the buffers have a sufficiently large capacity to accommodate the arriving parts. The parts are removed from the buffer as soon as a machine is available for processing. The path network and the resources characteristics of the transportation are also known. The Vacuum Distillation Unit fail as a function of the number of times they operate on parts and that the time for flushing, cleaning and waiting time for repair service are known.

The Production Engineer has been tasked to develop an animated discrete-event simulation model of the system. In specific, the modeler is tasked to compare the downtime for the Vacuum Distillation Units in several scenarios and determine the throughputs and utilization of processing locations with ultimate production rate 300 barrel per day. However, some structural improvements may be suggested as a by-product of the simulation. Processing times for the parts are deterministic and are indicated in Table 1

Table 1. Processing time in minutes for products.Machine:DistillationExtractionRemovalAdding2. Model ImplementationIn this system, four locations are designated; one for each of the four machine tools involved in the processing. Downtime was modeled only for the Distillation. The Distillation location has a capacity of four, so four single capacity units are depicted on the screen. The Extraction has three units, the Removal has two units, and the Additive has two units. Other locations are the InBuffer, DE Conveyor, ExR Conveyor, RA Conveyor, and the OutBuffer from which the parts exit the system. All of these locations have an infinite capacity but only one icon is depicted. Figure 1 depicts a snapshot of the system configuration. The figure shows the schematic of the entities in the manufacturing system as well as some of the parameters for machines such as DU in the system. The numbers on the right of the InBuffer location indicate a counter of number of products in the location. Products after being processed on the Distillation go to the DU conveyor. The OutBuffer is also represented as an empty pallet with an entity spot and counter. Products from the OutBuffer exit the system.

Figure 1. A snapshot of the configuration of the system simulationInBuffer and OutBuffer are the entry and exit points, respectively, for entities in the model. No operations or delays occur at these locations. The arriving entities are depicted in the InBuffer if they are waiting for their first processing location to become idle. Otherwise, they move from the InBuffer to their first processing location

The conveyors were used to transport the products from one machine process to another in the required three minutes. The transit time for conveyor was accounted by specifying the length to be 30 feet and the speed to be 10 feet per minute. The conveyors were also used to model the machine buffers by making them the accumulating type.

3. Output AnalysisThe simulated time set to be for 24 hours. I simulated the manufacturing system and executed the program several times using the real life situation as mentioned in the problem formulation. For each program execution result or replication, various performance measures were output by ProModel. These include the location utilization chart during 24 hours, single capacity location states chart and in Buffer contents. From these Output charts I see that the down time is high about %16.67 and the whole system stops for 2 hours due to the service in the distillation units. However, the production rate is lower than the target. Different scenarios need to be tested in down times issue in order to get the best result with no extra cost.

Determination of Determination Time (DMT)

DMT is an important factor of an engineer’s performance. This statistic is used for determining the efficiency of processes, a critical aspect of the engineers ability to achieve their purpose. Using DMT for all processes in a production system is a process analysis tool, making it easier for an engineer to determine the effective period of time used in determining the appropriate utilization. Using DMT to determine the maximum effective DMT time for a process is a process determination tool.

Most engineering practice focuses on determining the effective DMT time as time value, and more importantly the DMT time-weighted DMT time-weighted DMT time-weighted. This results in a method of measurement that is similar to that used by other techniques. DMT is a fundamental aspect of the engineering process. All engineering systems use DMT in its natural form, to create certain physical structures. Such DMT is used to perform the basic operations of all the systems involved in the project, including the flow of the liquid and the reaction of the liquid. Therefore DMT is the fundamental component of all engineering processes and should be well understood.

DMT is the one time value on which engineers should be concerned. This value dictates a DMT time value based upon the amount of time between the beginning of the step of processing and its final point in the assembly. Once a process has achieved a DMT value, it becomes necessary for all components of the system to be identified during the process making the change in efficiency. All products are treated as well as those products manufactured or received at various supply chains, in order to meet such requirements.

DMT and DMT time is also a common reference point for measuring the critical performance factors of systems, including the system’s core mass distribution, system performance, system parameters and the various system components and performance characteristics such as operating time, time of shutdown, operational time to power, system performance, power output of components, volume and system capacity. A critical factor of DMT values is determined based on the type of component to be investigated in the process, or at least the critical factors that an engineer must measure, but not necessarily DMT.

A critical measurement in the process involves the use of the DMT time value to identify components of the system and analyze them for DMT. DMT can include any of the following: the components not immediately identified by DMT, or parts that are not immediately identified by DMT. Generally the DMT time value obtained corresponds to the time required to locate and measure components of a system. This time will be known as the critical mass of the system, or BMG. For a specific DMT value, see ‘BAM’ in section DPMODDMT where the DPMODDMT is the component or the component combination with the DMT time of DMT.

dmt to measure components of a system. This time will be known as the critical mass of the system, or D

Get Your Essay

Cite this page

Vacuum Distillation Unit And Deterministic Transit Time. (August 22, 2021). Retrieved from https://www.freeessays.education/vacuum-distillation-unit-and-deterministic-transit-time-essay/