REQUEST FOR PROPOSAL
GENERAL CONTRACTING
Cement Production Plant
Environmental Impact Study in
Frederick County, Maryland
Page
Table of Contents
PROJECT SUMMARY
Introduction
Project History
Project Objectives
Project Schedule
Maps of Project Site
5 – 6
SCOPE OF WORK AND EXPECTED DELIVERABLES
PROPOSAL SUBMISSION REQUIREMENTS
Letter of Intent
Statement of Experience
Company Qualifications
References
Team Qualifications
Project Understanding
Approach
Schedule
Compensation
SELECTION AND EVALUATION CRITERIA
PROPOSAL SUBMISSION AND SCHEDULE
Process Schedule
RFP Contact
PRE-PROPOSAL ACTIVITIES
Pre-Bid Meeting
Questions and Clarifications
SUPPLIER LIST*
* Supplier List found using Google.com and searching under “Environmental Consultants”.
PROJECT SUMMARY
Introduction
General Contracting is planning on building a cement production plant in the town of Middletown, in Frederick County, Maryland. As part of the process an environmental impact study must be undertaken before the county can issue a permit to begin construction.

Project History
General Contracting has been producing building materials since 1964. It produces cement, gravel, and asphalt for construction contractors in the Pennsylvania, Maryland, and Virginia area. It is the number one producer of building materials in this region.

Project Objectives
General Contracting is planning on expanding its current cement production facilities in Maryland by building a new facility in Middletown, in Frederick County. The cement production plant will double the total current production in Maryland by increasing output by 2400 cubic yards of cement per week.

The new cement production plant will run from the hours of 8:00am to 5:00pm and will close for 1 hour for lunch at 12:00pm on Monday through Saturday. On Sunday the plant will be closed.

During each day that the plant is operating it will produce 400 cubic yards of cement. The production of cement will produce some effects to the environment which must be analyzed for negative impacts.

On any given day there will be approximately 20 fulltime employees running the plant, including management. Approximately 100 cement trucks will come in and out of the plant during the day with an estimated weight of 5 tons each.

Project Schedule
Develop Plans for
01/01/2004 – 09/30/2005
Cement Production Plant
Procure and Develop
10/01/2005 – 02/28/2006
Environmental Study
Apply for and Receive
03/01/2006 – 05/31/2006
County Permits
Construction of Plant
06/01/2006 – 12/31/2006
Begin Production of Cement
01/01/2007
Maps of Project Site
Map center is UTM 18 281018E 4369108N (WGS84/NAD83)
Middletown quadrangle
Projection is UTM Zone 18 NAD83 Datum
SCOPE OF WORK AND EXPECTED DELIVERABLES
The environmental impact study must be submitted following the rules, regulations, and format prescribed by County of Frederick Building Permits Division and the State of Maryland Building Permits Division.

The environmental impact study must be completed in a 3 month time frame, beginning on 01/01/2006 and ending on 02/28/2006.
The environmental impact study will describe the current existing environmental conditions of Middletown, Maryland by the cement production plant. These will include:

Air Quality
Water