A&d High Tech – Procurement Management Plan
Procurement Management PlanA&D High Tech Version 1.0March 29th, 2018Prepared byTeam 1Version HistoryVersion #DateAuthorKey differencesTable of ContentsIntroduction        4Procurement Management Approach        4Procurement List        4Type of Contract to be Used        4Contract Approval Process        5Sponsor Acceptance        7IntroductionThis Project Procurement Management Plan describes how the goods and services will be procured. This plan identifies and defines the items to be procured, the types of contracts to be used and the contract approval process.

Procurement Management ApproachThe Project Manager (PM) will be involved in all procurement activities under this project. The PM will work with the project team to identify the all the items to be procured and, will review and approve the procurement list prior to sending it to the procurement department. The procurement department will begin vendor selection and the contracting process. Procurement ListThe following procurement items have been determined to be essential for project completion and success.  QtyItemClassificationJustificationNeeded By12Windows 2000 work stationGoodsRequired for creating development environment, testing and operationWeek 25Windows 2000 serverGoodsRequired for creating development environment, testing and operationWeek 23Software DeveloperServicesRequired for unit designing, building, testing and deploymentWeek 1As RequiredSoftware LicenseServicesRequired for software development and TestingWeek 1Type of Contract to be UsedAll goods to be procured for this project will be solicited under RFQ.  The Infrastructure Lead will manage the purchasing of goods and define the quantities and required delivery dates.

Get Your Essay

Cite this page

Development Environment And D High Tech. (June 8, 2021). Retrieved from https://www.freeessays.education/development-environment-and-d-high-tech-essay/