Pages • 3
Construction Essay Preview: Construction Report this essay OVERALL ASSESSMENT OF PROJECT TIME & COST FACTORS ACTIVITY DURATION START FINISH Preliminary Building Programme 1/09/2001 31/08/2003 Design 1/09/2001 16/08/2002 Architectural 1/09/2001 1/07/2002 Structural 1/09/2001 16/08/2002 Services 18/10/2001 22/04/2002 Construction 18/10/2001 27/06/2003 Sub-structure 5/11/2001 18/03/2002 Super-structure 19/03/2002 27/06/2003 Commissioning 28/06/2003 31/08/2003 Summary of construction programme from start to.