Busn 6110 Essay Preview: Busn 6110 Report this essay Chapter 4 – Objective question 5 [pic 1]b. Critical path = A-C-D-E-G c. 26 weeks = 6+7+2+4+7d. 6 weeks, 15-9Chapter 4 – Objective question 20[pic 2]BCWS (Budget cost of work scheduled)Activity 1: 100% of 1,420,000 = $1,420,000Activity 2: 100% of 10,500,000=.