Construction Essay title: Construction OVERALL ASSESSMENT OF PROJECT TIME & COST FACTORS ACTIVITY DURATION START FINISH Preliminary Building Programme 1/09/2001 31/08/2003 Design 1/09/2001 16/08/2002 Architectural 1/09/2001 1/07/2002 Structural 1/09/2001 16/08/2002 Services 18/10/2001 22/04/2002 Construction 18/10/2001 27/06/2003 Sub-structure 5/11/2001 18/03/2002 Super-structure 19/03/2002 27/06/2003 Commissioning 28/06/2003 31/08/2003 Summary of construction programme from start to completion. In this.
Essay On Total Project Duration
Pages • 1
Pages • 1
Toy City Case Study Question 1We have the total project duration of 313 hours with cost of $19,350.If I were Bert, I would have a accommodated John’s vacation request. We could see in the below network diagram, Audit of Receivables (Activity 8) is not a critical activity that the early start is not equal to late start.