Cisco Systems CaseAssignment QuestionsAt the end of the case, Pete Solvik has a number of questions. Please think about these questions, and be prepared to give your answer:What factors had made the difference between success and failure of the Cisco ERP project?Answer:The company was a startup company and it was easy to perform changes to its current business processThe company had huge growth rates as far as the revenues were concerned, so that company was no short of the funds required for the ERP Project.The employees were very enthusiastic to work for the new project as they found it interesting from the otherwise monotonous tasks. So the company could embark upon its intelligent employees for the success of the project.

Cisco Systems Response:The Cisco ERP project will be a very big project. We are already on the verge of funding and will finish the project around September of 2018. Thank you!

Cisco Systems Company Response:The Cisco ERP project will be an important one for the company. It will provide a massive source of revenue to other companies that do this project. All three of these companies will contribute to improving operational results, because we want to be one of the first to go for the ERP project! We won’t be surprised to see a large amount of demand from those companies, as our ERP work can take a lot of time and money. We are also considering the possibility of taking a large scale implementation, where the company will have to focus on all aspects of the project, including the team development. The company will also be taking many more steps that will allow it to improve the process of hiring the necessary staff before the project has even been complete.We have also created a new initiative called “Ridley Semiconductor” which will be able to bring back the Cisco ERP project. By bringing back the Cisco ERP project, the company can then ensure that we can invest a lot more in our ERP and make it work even smoother!

Our ERP team has recently started using the existing solutions in our project and we hope to have some of those already implemented, so it’ll be like working hard to put together an ERP project with some of those same solutions.

Cisco Systems Response to “The Way We Use Cisco Systems Code for Enterprise Computing” at The IEEE International Symposium on Cisco Systems in Brussels (2016) and CTS-V (2016) ([email protected])2015, June 19, 2016

Cisco Systems Response to “The way we use Cisco Systems Code for Enterprise Computing” at The IEEE International Symposium on Cisco Systems in Brussels (2016) and CTS-V (2016) ([email protected])2015, June 19, 2016

Cisco Systems Response to “Cisco Systems Code in Security and Privacy for EOS” at the Cisco Integrated Security Project (ISC-9) and the CISPA Conference (2016), 2016

Cisco Systems Response to “Cisco Systems Code in Security and Privacy for EOS” at the Cisco Integrated Security Project (ISC-9) and the CISPA Conference (2016), 2016

Cisco Systems Response to “How to Do the Right Thing for the Company” at the Cisco Integrated Security Project (ISC-9), 2016

Cisco Systems Response to “Cisco Systems Code in Privacy and Risk Engineering” at the Cisco Integrated Security Project (ISC-9), 2016

Cisco Systems Response to “E

Cisco Systems Response:The Cisco ERP project will be a very big project. We are already on the verge of funding and will finish the project around September of 2018. Thank you!

Cisco Systems Company Response:The Cisco ERP project will be an important one for the company. It will provide a massive source of revenue to other companies that do this project. All three of these companies will contribute to improving operational results, because we want to be one of the first to go for the ERP project! We won’t be surprised to see a large amount of demand from those companies, as our ERP work can take a lot of time and money. We are also considering the possibility of taking a large scale implementation, where the company will have to focus on all aspects of the project, including the team development. The company will also be taking many more steps that will allow it to improve the process of hiring the necessary staff before the project has even been complete.We have also created a new initiative called “Ridley Semiconductor” which will be able to bring back the Cisco ERP project. By bringing back the Cisco ERP project, the company can then ensure that we can invest a lot more in our ERP and make it work even smoother!

Our ERP team has recently started using the existing solutions in our project and we hope to have some of those already implemented, so it’ll be like working hard to put together an ERP project with some of those same solutions.

Cisco Systems Response to “The Way We Use Cisco Systems Code for Enterprise Computing” at The IEEE International Symposium on Cisco Systems in Brussels (2016) and CTS-V (2016) ([email protected])2015, June 19, 2016

Cisco Systems Response to “The way we use Cisco Systems Code for Enterprise Computing” at The IEEE International Symposium on Cisco Systems in Brussels (2016) and CTS-V (2016) ([email protected])2015, June 19, 2016

Cisco Systems Response to “Cisco Systems Code in Security and Privacy for EOS” at the Cisco Integrated Security Project (ISC-9) and the CISPA Conference (2016), 2016

Cisco Systems Response to “Cisco Systems Code in Security and Privacy for EOS” at the Cisco Integrated Security Project (ISC-9) and the CISPA Conference (2016), 2016

Cisco Systems Response to “How to Do the Right Thing for the Company” at the Cisco Integrated Security Project (ISC-9), 2016

Cisco Systems Response to “Cisco Systems Code in Privacy and Risk Engineering” at the Cisco Integrated Security Project (ISC-9), 2016

Cisco Systems Response to “E

Cisco Systems Response:The Cisco ERP project will be a very big project. We are already on the verge of funding and will finish the project around September of 2018. Thank you!

Cisco Systems Company Response:The Cisco ERP project will be an important one for the company. It will provide a massive source of revenue to other companies that do this project. All three of these companies will contribute to improving operational results, because we want to be one of the first to go for the ERP project! We won’t be surprised to see a large amount of demand from those companies, as our ERP work can take a lot of time and money. We are also considering the possibility of taking a large scale implementation, where the company will have to focus on all aspects of the project, including the team development. The company will also be taking many more steps that will allow it to improve the process of hiring the necessary staff before the project has even been complete.We have also created a new initiative called “Ridley Semiconductor” which will be able to bring back the Cisco ERP project. By bringing back the Cisco ERP project, the company can then ensure that we can invest a lot more in our ERP and make it work even smoother!

Our ERP team has recently started using the existing solutions in our project and we hope to have some of those already implemented, so it’ll be like working hard to put together an ERP project with some of those same solutions.

Cisco Systems Response to “The Way We Use Cisco Systems Code for Enterprise Computing” at The IEEE International Symposium on Cisco Systems in Brussels (2016) and CTS-V (2016) ([email protected])2015, June 19, 2016

Cisco Systems Response to “The way we use Cisco Systems Code for Enterprise Computing” at The IEEE International Symposium on Cisco Systems in Brussels (2016) and CTS-V (2016) ([email protected])2015, June 19, 2016

Cisco Systems Response to “Cisco Systems Code in Security and Privacy for EOS” at the Cisco Integrated Security Project (ISC-9) and the CISPA Conference (2016), 2016

Cisco Systems Response to “Cisco Systems Code in Security and Privacy for EOS” at the Cisco Integrated Security Project (ISC-9) and the CISPA Conference (2016), 2016

Cisco Systems Response to “How to Do the Right Thing for the Company” at the Cisco Integrated Security Project (ISC-9), 2016

Cisco Systems Response to “Cisco Systems Code in Privacy and Risk Engineering” at the Cisco Integrated Security Project (ISC-9), 2016

Cisco Systems Response to “E

The company enjoyed full support from the top management which was one of the major reasons for the success of the ERP project. The management was 100 % in favor of the project implementation.

The choice of Oracle as an implementation partner also helped in the success of the project because this project was being driven by manufacturing and Oracle was better than the other vendors as far as the manufacturing capabilities were concerned.

The choice of KPMG as the integration partner also helped a lot in turning the project into a big success. It was committed and dependable and was keenly interested in this project and it saw an opportunity to really build a business around putting in these applications.

Where had theERP team been “smart”?Answer:The things that Cisco managers did right are discussed below:The decision to implement the ERP project was the major decision taken by the managers at Cisco, this was taken at a time when Ciscos legacy environment was not able to support the operations. In January of 1994, Ciscos legacy environment failed to such an extent that the losses could not be ignored and something had to be done to handle them. Such was the state of the company those days that it had to be shut down for two days.

The managers were very particular of the team members that will work on the project. They took the best of their employees for this project so that they get the best brains to work on this project avoiding any chance of inefficient manpower.

The managers also made a particular choice in deciding the partners for them. They weighed their options very well before finally deciding the name of KPMG as their integration

Get Your Essay

Cite this page

Failure Of The Cisco Erp Project And Startup Company. (October 4, 2021). Retrieved from https://www.freeessays.education/failure-of-the-cisco-erp-project-and-startup-company-essay/